THOMAS COUNTY, GEORGIA |
|
2010 REPORT ON PROJECTS FUNDED THROUGH |
|
2000 SPECIAL PURPOSE LOCAL OPTION SALES TAX |
| |
|
|
|
|
|
| |
Original |
Revised |
Expenditures |
| |
Estimated |
Estimated |
Prior |
Current |
|
|
Project |
Cost |
Cost |
Years |
Years |
TOTAL |
|
Thomas County Road Projects: |
|
|
|
|
|
|
Road construction
equipment |
210,000 |
210,000 |
364,856 |
0 |
364,856 |
|
Debt service on
road |
|
|
|
|
|
|
construction
equipment |
334,000 |
334,000 |
331,283 |
0 |
331,283 |
|
Road construction |
3,456,000 |
3,456,000 |
2,505,548 |
377,036 |
2,882,584 |
| |
|
|
|
|
|
| Road
projects - pass through to: |
|
|
|
|
|
|
City of
Thomasville |
3,200,000 |
3,200,000 |
3,284,304 |
0 |
3,284,304 |
|
City of Barwick |
44,000 |
44,000 |
45,081 |
0 |
45,081 |
|
City of Boston |
252,000 |
252,000 |
258,614 |
0 |
258,614 |
|
City of Coolidge |
112,000 |
112,000 |
115,174 |
0 |
115,174 |
|
City of Meigs |
196,000 |
196,000 |
200,950 |
0 |
200,950 |
|
Town of Ochlocknee |
108,000 |
108,000 |
110,857 |
0 |
110,857 |
|
City of Pavo |
88,000 |
88,000 |
90,518 |
0 |
90,518 |
| |
|
|
|
|
|
|
Emergency services equipment |
|
|
|
|
|
| |
|
|
|
|
|
|
Emergency Services Agency |
6,000,000 |
6,000,000 |
5,040,487 |
0 |
5,040,487 |
| |
|
|
|
|
|
|
Emergency services equipment |
|
|
|
|
|
| &
buildings |
0 |
0 |
1,145,691 |
0 |
1,145,691 |
| |
|
|
|
|
|
|
TOTALS |
$14,000,000 |
$14,000,000 |
$13,493,363 |
$377,036 |
$13,870,399 |
| |
|
|
|
|
|
|
Note: Expenditures also include interest income spent on
projects or passed through to other cities |
|
and the Thomas
County Emergency Services Agency. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
THOMAS COUNTY, GEORGIA |
|
2010 REPORT ON PROJECTS FUNDED THROUGH |
|
2006 SPECIAL PURPOSE LOCAL OPTION SALES TAX |
| |
|
|
|
|
|
| |
Original |
Revised |
Expenditures |
| |
Estimated |
Estimated |
Prior |
Current |
|
|
Project |
Cost |
Cost |
Years |
Years |
TOTAL |
| |
|
|
|
|
|
|
Judicial Building |
10,000,000 |
11,868,768 |
4,685,685 |
7,654,020 |
12,339,705 |
|
Rehabilitation of
Courthouse |
6,000,000 |
4,131,232 |
4,124 |
3,364 |
7,488 |
|
Justice Center
Roof Replacement |
0 |
0 |
403,202 |
498,777 |
901,979 |
|
Road construction |
7,325,599 |
7,325,599 |
0 |
0 |
0 |
| |
|
|
|
|
|
|
Capital Outlay - pass through to: |
|
|
|
|
|
|
City of
Thomasville |
10,231,200 |
10,231,200 |
4,197,767 |
1,987,388 |
6,185,155 |
|
City of Barwick |
122,040 |
122,040 |
50,072 |
23,706 |
73,778 |
|
City of Boston |
503,280 |
503,280 |
206,491 |
97,761 |
304,252 |
|
City of Coolidge |
198,360 |
198,360 |
81,385 |
38,531 |
119,916 |
|
City of Meigs |
381,240 |
381,240 |
156,419 |
74,055 |
230,474 |
|
Town of Ochlocknee |
213,480 |
213,480 |
87,589 |
41,468 |
129,057 |
|
City of Pavo |
152,640 |
152,640 |
62,627 |
29,650 |
92,277 |
| |
|
|
|
|
|
|
Capital Outlay - pass through to: |
|
|
|
|
|
|
Thomas County Library |
1,000,000 |
1,000,000 |
333,312 |
166,656 |
499,968 |
| |
|
|
|
|
|
|
TOTALS |
$36,127,839 |
$36,127,839 |
$10,268,673 |
$10,615,376 |
$20,884,049 |
| |
|
|
|
|
|
|
Note: Expenditures also include interest income spent on
projects or passed through to other entities. |
|
|
 |